will this Brexit going to scupper the new development on the sea front carpark as well then .
Does seem like the perfect excuse for it to not go ahead.
Who would benefit from an excuse, or a delay?....Certainly not Ron.
Have read though some of the new stuff (there are 100's and 100's of new pages).
This bit I thought was interesting and gives an over view timetable and phasing of the building of the Fossetts scheme.
View attachment 6084
More here
http://publicedrms.southend.gov.uk/...arch&viewdocs=true&SDescription=17/00733/FULM
Dear Mary,
Thank you for submission of additional documentation and revised plans in relation to the above application. In order to minimise the need for future reconsultation, I'd be grateful if you could confirm that the submitted documents reflect our previous discussions and include all the information required to address the concerns we have raised and (with the exception of the SAM management plan, which I understand will be submitted presently). If so, we will carry out reconsultation on that basis.
Kind Regards
Charlotte Galforg
Team Leader Development Control
Southend-on-Sea Borough Council
Charlotte Galforg,
Southend Borough Council
I can confirm that as far as the applicant's team is concerned that there are no further amendments expected or required, other than as you say the Scheduled Monument management plan.
Kind regards
Mary Power
Director
PowerHaus Consultancy
Does anyone know what the “SAM managent plan” is that we still need to submit?reply
Looks promising,that the final piece of plan/paperwork has been submitted to allow the council to finally review the application for the Fossetts Farm development.
Fingers crossed.
Does anyone know what the “SAM managent plan” is that we still need to submit?
The plans will NOT be discussed at the next Development Control Meeting on the Weds 6th March 2019 (the next scheduled meeting)
https://democracy.southend.gov.uk/ieListDocuments.aspx?CId=135&MId=3351&Ver=4
Next meeting after that is Weds 3rd April 2019 which is also after the current agreed determination deadline which was agreed and extended from 31st Dec 2018 to 31st March 2019 on the 10th December 2018.
So it looks like yet another extension to the determination date will be required.