Westcliff Shrimper
Director of Footballs⭐
Good chat last night.
Thanks again for your time, Naps. Much appreciated by all.
Good chat last night.
Well the project is becoming a farce... to not have permission at the training centre at this stage is beyond incompetence. What a mess ....It's not the only application that is delayed. The temporary buildings at the training centre still don't have permission from Rochford Council.
Makes you wonder what's going on.
Not a lot by the looks of it.It's not the only application that is delayed. The temporary buildings at the training centre still don't have permission from Rochford Council.
Makes you wonder what's going on.
Just an observation - I note Liam mentioned that the ultimate capacity of any reduced scope stadium at FF might be larger with the introduction of safe-standing.
That isn't the case unfortunately - safe-standing replaces seating at a 1:1 ratio.
Its for the temporary portacabins that won't be needed until end June/ beginning July - not the planning for the final structures that happen at a much later stage og the development. So hardly a desperate rush. That said a frustration is we don't actually know how minor the outstanding points on theses applications are? They could be minor stuff that could be satisfied in a week or two or more challenging. We are not told. And the end date for the determination isn't until April.Well the project is becoming a farce... to not have permission at the training centre at this stage is beyond incompetence. What a mess ....
No - the planning permission for RH states that the new stadium for Southend has to be the one at Fossets Phase 1Interesting stuff from Trevor re the RH and FF building scenario. If I understood correctly, the developers can start building on the Roots Hall car park but can't start demolishing the old stadium until SUFC have a place to play (or words to that effect). In my mind everyone assumes that means the stadium at FF has to have been built, but I was thinking what if SUFC agreed to groundshare with Dagenham or Col Utd or similar? They'd have somewhere to play so that would pass the test surely? Regarding FF the building of houses & flats there can't finish - not sure how far they can be completed - till there's a stadium for a football club to play in. As Trevor said, this could mean Southend Manor / Leigh Ramblers / even a phoenix club as it doesn't stipulate SUFC!
So I reckon one possible way it might work out is :-
- SUFC club agree as soon as this season ends to a ground share scheme and start playing there next season
- Building the flats and houses work starts on the whole RH site asap after that agreement is reached
- Building work starts on Boots and Laces in the summer once the new training pitches are fully ready to be used (don't think anyone actually has to train there), followed asap thereafter with work to build the stadium assuming the planning application has been fully passed!
- Stadium at FF is fully completed and either a phoenix club, or even SUFC if it has managed to exist whilst in the groundshare phase, sign to lease the new stadium off Ron or son Jack or whoever owns it
- Rest of houses and flats are built at FF to complete the whole deal
- Ron, Jack and the rest of the Martin family ride off into the sunset at least as far as running a football club is concerned :)
Damn, I thought it was 3 standing for every 2 seats. That's a shame.Just an observation - I note Liam mentioned that the ultimate capacity of any reduced scope stadium at FF might be larger with the introduction of safe-standing.
That isn't the case unfortunately - safe-standing replaces seating at a 1:1 ratio.
That is correct, an application with delegated decision does not have to go before Development Control Committee.The application has been given delegated decision - I think that means it won't be voted on by councillors and get just be approved (or rejected) by planning staff
Unfortunately not - the systems can come in 1,2 or 3 seat modules, but it is a like for like conversion.Damn, I thought it was 3 standing for every 2 seats. That's a shame.
What I was told, and what I relayed, was that no application had been received.@Cockle43 can you clarify again what you were told? That the council is awaiting a revised planning application? If so then, since there is already one registered on the planning portal, there must be a third revised application on the way?
Thanks for clearing that up Trevor, that would make sense.What I was told, and what I relayed, was that no application had been received.
I received that information on Monday and digging deeper it appears that all of the statutory body consultations to all interested bodies were completed by 1/12/22 on 22/01528/FULM which went in on 29/7/22; as you would expect for the application just being on the same footprint most of those would not be varied very much or at all. The determination deadline was set as 13/12/23 and an agreed Expiry date is now shown as 5/4/23.
Looking at that I would say that what the information I was given should have said that the application has not been submitted for decision rather than just not submitted.
This ties in with the Council statement which stated that is has not progressed to decision because of some details still required from the Club. That does not make it quite as horrendous as nothing been submitted but it still means the ball is firmly in the Club's hands to move it forward towards completion.
The question remains as to why the Club's planning agents at Power Haus Consultancy have not moved it forwards when it is in their, and the Club's, hands to do so.
The question remains as to why the Club's planning agents at Power Haus Consultancy have not moved it forwards when it is in their, and the Club's, hands to do so.
As a former planning officer (many many years ago, and not in Southend) this makes more sense.What I was told, and what I relayed, was that no application had been received.
I received that information on Monday and digging deeper it appears that all of the statutory body consultations to all interested bodies were completed by 1/12/22 on 22/01528/FULM which went in on 29/7/22; as you would expect for the application just being on the same footprint most of those would not be varied very much or at all. The determination deadline was set as 13/12/23 and an agreed Expiry date is now shown as 5/4/23.
Looking at that I would say that what the information I was given should have said was that the application has not been submitted for decision rather than just not submitted.
This ties in with the Council statement which stated that is has not progressed to decision because of some details still required from the Club. That does not make it quite as horrendous as nothing been submitted but it still means the ball is firmly in the Club's hands to move it forward towards completion.
The question remains as to why the Club's planning agents at Power Haus Consultancy have not moved it forwards when it is in their, and the Club's, hands to do so.
The potential for starting some works at Roots Hall is there but would need some clever footwork around Condition 3 using the phasing plan required under Condition 2 of the application 19/01985/FULM for the Roots Hall site.Interesting stuff from Trevor re the RH and FF building scenario. If I understood correctly, the developers can start building on the Roots Hall car park but can't start demolishing the old stadium until SUFC have a place to play (or words to that effect). In my mind everyone assumes that means the stadium at FF has to have been built, but I was thinking what if SUFC agreed to groundshare with Dagenham or Col Utd or similar? They'd have somewhere to play so that would pass the test surely? Regarding FF the building of houses & flats there can't finish - not sure how far they can be completed - till there's a stadium for a football club to play in. As Trevor said, this could mean Southend Manor / Leigh Ramblers / even a phoenix club as it doesn't stipulate SUFC!
So I reckon one possible way it might work out is :-
- SUFC club agree as soon as this season ends to a ground share scheme and start playing there next season
- Building the flats and houses work starts on the whole RH site asap after that agreement is reached
- Building work starts on Boots and Laces in the summer once the new training pitches are fully ready to be used (don't think anyone actually has to train there), followed asap thereafter with work to build the stadium assuming the planning application has been fully passed!
- Stadium at FF is fully completed and either a phoenix club, or even SUFC if it has managed to exist whilst in the groundshare phase, sign to lease the new stadium off Ron or son Jack or whoever owns it
- Rest of houses and flats are built at FF to complete the whole deal
- Ron, Jack and the rest of the Martin family ride off into the sunset at least as far as running a football club is concerned :)